“A yard” is the unit every concrete conversation happens in — the truck sells by the yard, the price is per yard, the short-load fee kicks in under a few yards. But a yard is a volume, and what you actually care about is area: how much patio, driveway, or sidewalk does that volume become at your slab thickness?

The short answer: one cubic yard covers 81 square feet at 4 inches thick. That single number answers most residential questions, and the table below extends it to every common thickness. The math is simple division — a yard is 27 cubic feet, and you divide by the thickness in feet — but getting it wrong means a short load or a wasted half-yard, so it is worth seeing the numbers laid out.

Coverage per cubic yard by thickness

Slab thicknessSquare feet per yardTypical use
3 in108 sq ftThin overlays, mudjacking (rare for new slabs)
4 in81 sq ftPatios, walkways, sidewalks, shed pads
5 in65 sq ftResidential driveways, garage floors
6 in54 sq ftRV pads, heavy loads, commercial work
8 in41 sq ftStructural slabs, heavy commercial

Each figure is 27 ÷ (thickness ÷ 12). At 5 inches: 27 ÷ 0.4167 = 64.8, rounded to 65. These are exact geometric coverage — always add 5–10% waste on top for the real order.

Common projects, translated to yards

ProjectSize & thicknessYards (exact)Order
Small patio10 × 10 ft, 4 in1.231.5 yd
Walkway4 × 30 ft, 4 in1.481.75 yd
2-car driveway20 × 20 ft, 5 in6.176.5 yd
Garage floor20 × 24 ft, 5 in7.418 yd
Shed pad8 × 10 ft, 4 in0.991.25 yd

The “order” column adds roughly 5–10% waste and rounds up to the nearest quarter-yard, which is how ready-mix is billed. Check any of these against our concrete calculator — same math, your exact dimensions.

What a yard costs in 2026

2026 pricing guides put standard residential ready-mix at roughly $125–$180 per cubic yard delivered (allbetterapp.com: $125–$195; buildestimatory.com: $125–$160; metalamericaconcrete.com: $120–$165). Treat these as planning ranges — your county, the mix design, and diesel prices move the real number. Three things that consistently surprise first-time buyers:

  • Short-load fees. Order under the supplier’s truck minimum (often 4–5 yards) and expect roughly $30–$60 extra per yard. A 1-yard order can cost nearly double the per-yard rate.
  • Strength upgrades are cheap. Going from 3,000 to 4,000 PSI typically adds $10–$25 per yard — trivial against the total, and the right call for driveways.
  • Delivery extras add up. Saturday delivery, long chute runs, pump trucks, and wait time are all separate line items. Ask for the all-in price, not the per-yard price.

Frequently asked questions

81 square feet. A cubic yard is 27 cubic feet; at 4 inches thick (one-third of a foot), 27 ÷ 0.333 = 81. At 5 inches it covers about 65 square feet, and at 6 inches about 54.

Related calculators & guides